Indian solar projects getting too big to bid: Domestic Developers

Developers wrote a letter asking MNRE to address their concerns, but were left disappointed

Image for representational purpose only

As the government pushes to meet its target of achieving 100 GW solar capacity by 2022, it has started to increase the maximum project bid size. While the government is trying to increase scale and bring down costs, it has gone too far according to some domestic project developers.

In light of some of the recent moves by the government agencies, these developers feel that this move is eventually going to be detrimental for them and have requested to the Ministry of New and Renewable Energy (MNRE) Secretary to intervene.

Let’s take the example of two recent announcements:

The Solar Energy Corporation of India (SECI) and the National Thermal Power Corporation (NTPC) increased the maximum bidding capacity by a single bidder in their respective tenders announced in the first quarter.

- Advertisement -

In February 2018, SECI tendered 3 GW of Inter-State Transmission System (ISTS) – connected solar PV projects to be developed across the country. After tendering the capacity, a revision was made and the maximum allowable capacity for a single bidder was more than doubled to 1,800 MW from the previous maximum allowable capacity of 750 MW for a single bidder, and the minimum allowable capacity was reduced to 200 MW from the previous 250 MW.

Then in March 2018, NTPC tendered 2,000 MW of grid-connected solar PV to be developed across the country. For this tender, the minimum project capacity to bid was 50 MW and the maximum allowable capacity to bid was set at 2,000 MW for this tender.

After the revision was announced to the maximum allowable project bid size by the implementing agencies, Indian solar project developers Adani Green, Azure Power, Hero Future Energies, Mytrah Energy, ACME Solar and Sprng Energy wrote to the Ministry of New and Renewable Energy (MNRE) and SECI, requesting SECI and NTPC to keep the bidding limit for a single bidder to 600 MW.

The developers also asked to defer the bid submission of both SECI 3 GW and NTPC 2 GW tenders until the appropriate amendments were put in place.

Key Points Raised in the Letter

  • Given the constraints in connectivity at ISTS where the existing transmission capacity is available, it would be difficult to get timely connectivity for such large-scale projects.
  • Large-scale land acquisition is an uphill task for the bidder. Timely execution of such projects would be difficult, and the lenders may not come forward to finance such high-risk projects specifically on two counts – land and transmission infrastructure.
  • Such a large bid size will prohibit some of the serious players based on financial criteria such as net worth requirement, turnover requirement, line of credit etc. Restricted competition may not provide the desired tariff levels.
  • Given the current banking scenario in the country, accessing credit lines with a bank guarantee for all domestic players in such huge numbers would make them non-competitive compared to foreign players who would have an undue advantage in accessing these lines of credit.

However, the letter by the domestic developers has been ignored so far and on June 26, 2018, SECI finished accepting the technical bids for the 3 GW tender which was oversubscribed by 2.1 GW . SoftBank backed SBG Cleantech ended up bidding for the maximum allowable capacity of 1,800 MW in the technical bids announced. ACME solar submitted a technical bid for 600 MW and Renew bid for 500 MW. No other developer bid for more than 300 MW capacity.

When contacted, a high-ranking SECI official told Mercom, “We are the tender issuing authority and it is within our powers to change the provisions of the tender document. By increasing the maximum allowable capacity to bid for, we just ensured that the capacity had takers. In no way are we in violation of any laws or government rules.”

An NTPC official aware of the development told Mercom, “We are unable to fathom why the developers are agitated. If we have allowed the maximum bid capacity to be 2 GW, it means more participation. It’s not that we have increased the minimum capacity to be bid for too. Had that been done, the developers’ concerns would be understandable.”

A recent SECI tender for 2 GW of ISTS-connected grid-connected solar PV tender was oversubscribed by 1.8 GW. For this tender, the maximum capacity to bid for was 600 MW. The developers in their letter have also quoted this tender’s oversubscription as an example and asked implementing agencies to adjust the cap to 600 MW, 750 MW levels.

When contacted, an official at the MNRE said, “Yes, we have received the communication, but see no cause for any intervention. It is a fair tender, plus it is a reverse auction, so everyone has equal chance of winning a contract.”

“It looks like the government is trying increase scale and reduce costs, which is understandable. Hopefully, this is well thought out. Even projects that are a few hundred megawatts in size have had land and evacuation issues in the recent past. No matter what, increasing the project size so high will definitely close the door on smaller developers in the country. Only a handful of companies will be able to participate in these mega-tenders going forward,” said Raj Prabhu, CEO of Mercom Capital Group.

The large-scale project development landscape is already getting consolidated with large corporate conglomerates and PE-funded developers dominating the landscape. According to the Mercom Market Share Tracker, in 2017, the top 10 utility-scale project developers accounted for 62 percent of all large-scale projects developed in the country.

(Source: Mercom India)

- Advertisement -
Loading form…

Industry's Buzz

CG Power Partners with IIT-Delhi to Research On Power, Semiconductors

0
The MoU aims to combine CG’s domain expertise and manufacturing strength and IITD’s research capabilities. CG Power and Industrial Solutions (CG) signed a five-year memorandum...

Protolabs Opens GCC in Hyderabad

0
President and CEO of Protolabs, Suresh Krishna said that India provides exceptional engineering talent that fits perfectly into Hyderabad’s strong technology ecosystem. Global digital manufacturing...
The internal manufacturing facility of Zelio E-Mobility

Zelio E-Mobility Gets BSE Approval to Raise $18M Capital for Future Expansion

0
Zelio reported a 120 per cent year-on-year (Y-o-Y) increase in consolidated operational revenue, from ₹134.78 crore in H1 FY26 to ₹296.66 crore. The rapidly expanding...
Image for representation purpose

Industrial CT And AI Expose Hidden Defects In Automotive Electrical Connectors

0
Two connectors may carry the same part number but differ in material and dimensions. Lumafield found such discrepancies in its examination of 1,451 automotive...
Frequency Electronics

Frequency Electronics’ Voyager Oscillators Put Precision Timing In Focus

0
Frequency Electronics supplied the quartz-based timing references for NASA's Voyager spacecraft. The technology, first developed in the 1970s, remains part of its business in...

Learn From Leaders

Rohin Y, CEO and Co-Founder, LightSpeed Photonics, India

“We reduce latency by shortening the distance signals travel through copper and extending that...

0
As AI data centres scale, how can optical connectivity overcome the limits of electronic interconnects? In an interview, Rohin Y of LightSpeed Photonics speaks...
SK Venkataraghavan, Director, Solutions and Services Group, Lenovo India

“Everybody wants to jump into AI, but many organisations are still not ready from...

0
In an exclusive interaction with EFY's Saba Aafreen, Lenovo's S. K. Venkataraghavan discusses the challenges of moving enterprise AI from pilots to production, with...
Santhosh Kumar, Managing Director at Texas Instruments India

“India Is Becoming A Place To Design Products For The World”- Santhosh Kumar, TI...

0
As Texas Instruments marks 40 years in India, Santhosh Kumar, managing director and president, TI India, speaks about the company’s evolution towards end-to-end product...

The Eye That Spots Defects Before They Happen

0
https://youtu.be/vanxJYT2LIo Most inspection machines tell you a board failed. Delvitech's tells you when it is about to.Every inspection stage in a factory traditionally needs its...
Pravin Patel, Founder and Chairman, Brio Agri, India

“Our goal is not to replace farmers, but to empower them with better tools,...

0
In an exclusive interaction with EFY's Saba Aafreen, Pravin Patel, Founder and Chairman of Brio Agri, discusses building hydroponics and controlled-environment agriculture in India,...

Startups

Jaisimha Rao, Founder and CEO, Niqo Robotics

“Our Robots Are Tractor-Mounted, With the Tractor Providing Propulsion, So the System Does Not...

0
A robot may work perfectly in a lab, but taking it to a real farm is a different test altogether. In an exclusive interaction...

RHIA’s PLC Slayer Eliminates Fragmented Architectures In Industrial Automation

0
The startup’s innovation integrates separate controllers, sensors, and motor drivers into a single, flexible industrial automation platform. Does building industrial-grade automation always have to be...

EVE NET Turns Spare Smartphone Capacity Into An AI Cloud

0
What if the phone in your pocket could help run AI? A Mumbai-based startup wants to cut AI computing costs by tapping into millions...

Vimag Labs’ Magnet-Free Motors Set To Redefine EV Efficiency

0
Can software replace rare-earth materials? This Bengaluru startup uses virtual magnets to eliminate traditional permanent magnets, boosting EV motor efficiency up to 95 per...

Pine Labs Q2 FY27 Profit Soars 6.5x

0
Pine labs said that it processes 25 million transactions per day, a 22 per cent increase from the previous year. Fintech company Pine Labs, reported...